Central WV pipeline complete and pumping gas

Photo submitted to The Exponent Telegram  This aerial photo shows the path of the Stonewall Gas Gathering Pipeline, which passes through Doddridge, Harrison and Lewis counties. The pipeline became operational on Nov. 30.
Photo submitted to The Exponent Telegram
This aerial photo shows the path of the Stonewall Gas Gathering Pipeline, which passes through Doddridge, Harrison and Lewis counties. The pipeline became operational on Nov. 30.

CLARKSBURG, W.Va. — An extra 700 million cubic feet of natural gas is now being pumped each day from North Central West Virginia thanks to the recent completion of the Stonewall Gas Gathering Pipeline.

That pipeline will carry up to 1.4 billion cubic feet of gas daily once fully operational, according to Dave Mashek, a spokesman for M3 Midstream (known as Momentum), which owns Stonewall Gas Gathering LLC.

Mashek said the company began acquiring rights of way from affected landowners for the project in 2013.

Precision Pipeline LLC began construction on the project early last spring, according to Mashek.

The pipeline started pumping gas Nov. 30 and is scheduled to reach full capacity by summer of 2016…